CEBU CITY, Philippines — Cebu City Mayor Nestor Archival Sr. has expressed support for hiring an independent project management consultant to oversee the completion of the long-delayed Cebu City Medical Center (CCMC), saying third-party oversight could help ensure the hospital is finally finished after more than a decade of construction.
The proposal comes as the city government continues efforts to complete one of Cebu City’s most important healthcare infrastructure projects, which has faced years of delays following the 2013 Bohol earthquake.
Third-Party Oversight Proposed
Archival made the statement during an interview on Wednesday, July 8, following a privilege speech delivered by Councilor David “Dave” Tumulak during a Cebu City Council session.
Tumulak proposed that the city hire an independent Project Management Consultant (PMC) to supervise the remaining construction works and provide technical oversight until the hospital is completed.
The mayor welcomed the proposal, emphasizing that completing the CCMC remains one of his administration’s top priorities.
“Yes, I’m inclined to support that. I also support it because what I really want is for the CCMC to finally be completed. For the last 10 to 12 years, it has remained unfinished,” Archival said.
Completing a Long-Delayed Hospital Project
The Cebu City Medical Center has undergone multiple construction phases over the years after the original hospital building was declared structurally unsafe following the magnitude 7.2 Bohol earthquake in 2013.
Several administrations have attempted to complete the project, but various technical, financial, and construction issues have contributed to repeated delays.
Archival said his administration carefully reviewed the project’s status before allowing construction to resume, even though the contract and Notice to Proceed had already been issued before he assumed office.
Phase 5 Construction Resumed
The city officially relaunched Phase 5 of the project in February 2026, with Dakay Construction and Development Corp. continuing the remaining work.
While construction has resumed, Archival acknowledged that completing the hospital presents unique engineering challenges because different contractors handled previous phases of the project.
He noted that integrating earlier construction work with ongoing developments requires careful technical evaluation.
Concerns Over Previous Construction
The mayor revealed that recent inspections raised concerns regarding portions of the work completed during earlier construction phases.
According to Archival, some previously installed components may no longer meet current engineering and technical standards.
Because of these findings, he believes an independent consultant could objectively evaluate completed works, monitor ongoing construction, and ensure that all systems comply with required specifications before the hospital becomes operational.
Budget Needed for Consultant
Although Archival supports hiring a third-party consultant, he acknowledged that the city currently has no allocated budget for the proposal.
He said funding may have to come from a supplemental budget, although he expects the required amount to be relatively modest.
“There is no budget allocated for that. We may have to source it through a supplemental budget, although I don’t think the amount needed will be that big,” the mayor explained.
The proposal will still require approval through the city’s budget process before implementation.
Focus on Mechanical and Electrical Systems
Among the biggest challenges facing the project are the hospital’s Mechanical, Electrical, Plumbing, and Fire Protection (MEPF) systems.
Archival said that while architectural works such as wall finishing and painting continue to progress, the MEPF components require comprehensive inspection and testing before additional construction can proceed.
Hospital infrastructure relies heavily on properly functioning electrical systems, plumbing, fire safety equipment, ventilation, and medical utility installations, making these components critical before the facility can open.
DOH Recommends Testing Existing Installations
The mayor disclosed that officials from the Department of Health (DOH) advised the city not to immediately replace existing MEPF installations.
Instead, the DOH recommended conducting technical tests first to determine whether previously installed systems remain functional and compliant with standards.
Following this recommendation, Archival instructed the city’s engineering team to formally require Dakay Construction to perform the necessary inspections and testing.
The evaluation results will determine whether any components need repair or replacement.
COA Approval Required for Replacements
If testing shows that previously installed systems are no longer usable, the findings must be submitted to the Commission on Audit (COA).
COA approval will be necessary before replacing any components that had already been installed under previous contracts.
The additional testing and documentation requirements are expected to ensure transparency while preventing unnecessary expenditures on functioning equipment.
Additional Time Granted to Contractor
Because of the extensive technical assessments required, the contractor has been granted an additional 145 days to complete portions of the project.
City officials said the extension will allow sufficient time for testing, validation, and any corrective work needed before construction advances to the next stage.
Despite the revised timeline, Archival reiterated that the city remains committed to completing the hospital as soon as possible.
Target Completion by End of 2026
The current Phase 5 covers the completion of the hospital’s fourth to seventh floors, which will significantly expand the facility’s capacity once operational.
The Cebu City Government continues to target:
- Completion of construction: End of 2026
- Full hospital operations: Early 2027
Once completed, the upgraded Cebu City Medical Center is expected to strengthen healthcare services for thousands of residents by providing expanded medical facilities, additional patient capacity, and improved hospital infrastructure.
For Archival, ensuring the successful completion of the long-delayed project remains a key priority, with independent oversight seen as a practical step toward delivering a fully functional and modern public hospital for the people of Cebu City.