CEBU CITY, Philippines — The Commission on Audit (COA) has flagged significant delays and management issues in the construction of the Cebu City Medical Center (CCMC), revealing that the flagship public hospital remains unfinished more than a decade after construction began despite over ₱1.13 billion already being spent on the project.
Originally envisioned as a modern replacement for the old Cebu City Medical Center that was heavily damaged during the 2013 Central Visayas earthquake and demolished the following year, the hospital was expected to improve healthcare services for city residents. However, according to COA’s latest audit report, the project continues to face major setbacks caused by planning deficiencies, engineering problems, and contract management issues.
Over ₱1.13 Billion Spent, Yet Project Remains Incomplete
The audit reported that the hospital project consists of five infrastructure contracts with a combined contract value of approximately ₱1.904 billion.
As of the end of 2025, the Cebu City Government had already disbursed ₱1.13 billion, but only the first phase of the project had been completed. The remaining phases remain unfinished due to repeated design revisions, inadequate engineering preparation, and multiple work suspensions.
COA said the absence of comprehensive detailed engineering studies before construction began resulted in numerous modifications after work was already underway, significantly extending the project’s completion timeline.
Major Design Changes Delayed Construction
Among the major revisions cited by auditors was the reduction of the hospital building from its original 10-story design to six stories.
The audit also noted changes involving hospital facilities, electrical and generator systems, and adjustments made after workers encountered previously unidentified underground structures during excavation.
Each modification required additional engineering work, contract amendments, and suspension orders that further delayed construction.
Contracts Extended and Eventually Terminated
COA found that Phase 3 of the project, originally scheduled for completion within 150 days, was extended to 1,034 days through a series of suspension and variation orders.
Auditors questioned one suspension order that granted an additional 574 days, noting that the city failed to provide sufficient documentation to justify the lengthy extension.
Although accounting records indicated that Phase 3 was nearly 92 percent complete by April 2023, the Department of Engineering and Public Works later concluded that the contract could no longer be completed.
The audit also identified a potential ₱1.22-million overpayment resulting from an unrecouped mobilization fee that should be recovered if the contract is formally terminated.
Meanwhile, Phase 4 was mutually terminated in January 2023 before major structural work could proceed.
At the time construction stopped, less than 20 percent of the project had been completed. The city’s Contract Termination Review Committee found that the contractor failed to comply with project instructions and did not maintain the minimum equipment required at the construction site.
Engineering Deficiencies Identified
Beyond project delays, COA also identified several engineering and construction deficiencies.
According to the audit, some structural components did not conform to approved plans, while portions of the plumbing and electrical systems had to be relocated after installation.
Several room layouts required demolition and reconstruction due to design inconsistencies.
By the end of 2025, some air-conditioning and mechanical systems remained incomplete or nonfunctional, while several building systems had yet to undergo the required testing before turnover.
Missing Documents Raise Accountability Concerns
COA also reported that between May 2025 and March 2026, the Department of Engineering and Public Works failed to submit critical project documents covering approximately ₱897.34 million worth of project components.
The missing records included approved engineering plans, detailed cost estimates, accomplishment reports, and other technical documents necessary for auditors to verify whether government expenditures were reasonable and properly supported.
Without these records, auditors said they could not fully determine the accuracy of project costs, increasing the risk of irregularities and possible loss of public funds.
COA Orders Corrective Measures
To address the audit findings, COA directed the Cebu City Government to submit all missing engineering records, justify the prolonged suspension orders, recover any validated overpayments, and explain why several completed systems remain nonfunctional.
During an exit conference held on April 8, 2026, the acting city engineer acknowledged the audit observations and committed to providing the required explanations and supporting documents.
COA also recommended broader reforms for future infrastructure projects, including ensuring that projects are fully implementation-ready before bidding, conducting comprehensive site investigations, strengthening engineering planning, and improving technical oversight throughout project implementation.
As of the audit period, no revised completion schedule has been announced for the Cebu City Medical Center. The project’s completion will largely depend on how the city resolves its unfinished contracts, addresses engineering deficiencies, and implements the corrective measures recommended by the Commission on Audit.